Legislation Details

File #: 6822    Version: 1 Name:
Type: Resolution Status: Passed
File created: 8/12/2024 In control: City Council
On agenda: 8/20/2024 Final action: 8/20/2024
Title: Consider A Resolution Authorizing The City Manager To Negotiate And Execute Contract Amendment No. 1 With AECOM For General Engineering Consultant Services Related To Project Management In An Amount Not To Exceed $500,000.00, For A Revised Contract Amount Not To Exceed $762,500.00.
Attachments: 1. Resolution
CC MEETING: August 20, 2024

DATE: August 12, 2024

TO: Erin Rinehart, City Manager

FROM: Jonathan Wheat, P.E., Director of Engineering
Krystle Boise, Director of Strategic Services

Title
Consider A Resolution Authorizing The City Manager To Negotiate And Execute Contract Amendment No. 1 With AECOM For General Engineering Consultant Services Related To Project Management In An Amount Not To Exceed $500,000.00, For A Revised Contract Amount Not To Exceed $762,500.00.

Body
BACKGROUND:
On February 20, 2024, City Council approved a Resolution authorizing the City Manager to execute a professional services agreement with AECOM for general engineering consultant services related to project management. The original contract provided for one project manager to oversee construction projects for the City. The current contractor is providing the City project management of three horizontal construction projects. Contract Amendment No. 1 will provide additional project management services focused on vertical construction projects similar to: City Jail Upgrades, Fire Station 5/South Service Center Construction, Oak Creek Tennis Center Improvements, and City Hall Phase 2.

A formal selection process was conducted, by which a Request for Qualifications (RFQ) was publicly advertised, and firms were evaluated on criteria that included their understanding of the required services, similar project experience, personnel depth and company qualifications. The most qualified firms were identified by staff and then approved by City Council.

FINANCIAL IMPLICATIONS:
Funding for these services will come from the respective capital project fund and is currently available.

Staff is proposing this contract amendment with a total amount not to exceed $500,000.00. Project selection will be based on individual capabilities, variability in project size and scope requirements.

IMPACT ON COMMUNITY SUSTAINABILITY:
This project will support the City Council's strategic object...