Consider Authorizing The City Manager To Execute Change Order No. 3 With Gomez Floor Covering, Inc. dba GFC Contracting For The City Hall Basement Remodel Project In An Amount Not To Exceed $28,138.00 Increasing The Total Project Contract To $961,946.00.
Body
BACKGROUND:
The City Council awarded a contract on February 18, 2025, to Gomez Floor Covering, Inc. dba GFC Contracting in the amount of $855,399.00. The scope of the project is to upgrade interior lighting, replace ceiling tiles and grids, and provide additional open office space in City Hall Basement. Change Orders 1-2 in the amount of $78,409.00 were approved by staff, and included basement floor plan modifications, additional offices on the first floor, new mailroom millwork, HVAC modifications, a domestic waterline relocation, replacement of a drain line under the employee restrooms, and additional electrical and data work.
During the Fire Inspection, the Fire Marshal noted multiple deficiencies in the sprinkler and fire alarm systems that were outside of the contractor’s scope of work. The existing sprinkler system needs to be repaired and adjusted to meet the current fire code.
During a door hardware meeting with Facilities and IT, both departments noted that additional door hardware items are needed.
This change order (Change Order 03) in the amount of $28,138.00, will cover the following items:
• Fire Sprinkler system repairs
• Fire Alarm system repairs
• Additional door hardware items
FINANCIAL IMPLICATIONS:
Gomez Floor Covering, Inc. dba GFC Contracting submitted a proposal to the City of Carrollton to cover the above-mentioned items in an amount not to exceed $28,138.00. The revised contract amount (Including Previous Change Orders 01 - 02) would be $961,946.00, a 12.45% increase from the original contract amount of $855,399.00. Funding is available from General Obligation bond funds.
IMPACT ON COMMUNITY SUSTAINABILITY:
This project will contribute to community sustainability by updating a key municipal facility to provide a better working and business environment for City employees and citizens, and provide for more cost-efficient energy components, and an upgraded office area for city personnel located in the basement.
STAFF RECOMMENDATION/ACTION DESIRED:
Staff recommends City Council authorize the City Manager to execute Change Order 03 with Gomez Floor Covering, Inc. dba GFC Contracting for the City Hall Basement Remodel Project in an amount not to exceed $28,138.00.