Legislation Details

File #: 7702    Version: 1 Name:
Type: Status: Passed
File created: 7/23/2026 In control: City Council
On agenda: 8/11/2026 Final action: 8/11/2026
Title: Consider Authorizing The City Manager To Execute Change Order No. 3 With Millis Development & Construction - Dallas, LLC For Additional Work On The Woodlake Lake Enhancements Project In An Amount Not To Exceed $127,078.96, Increasing The Total Construction Contract Amount To $3,992,058.21.
Attachments: 1. Map

City Council Meeting Date: August 11th, 2026

 

Date: July 23th, 2026

 

To: Erin Rinehart, City Manager

 

From: Jonathan Wheat, Director of Engineering

         Shannon Hicks, Assistant City Manager

 

Title

Consider Authorizing The City Manager To Execute Change Order No. 3 With Millis Development & Construction - Dallas, LLC For Additional Work On The Woodlake Lake Enhancements Project In An Amount Not To Exceed $127,078.96, Increasing The Total Construction Contract Amount To $3,992,058.21.

 

Body

Summary:

The purpose of this item is to approve construction items required to finish the Woodlake Lake Ph 1 Project.

 

Background:

The City has an existing construction contract with Millis Development & Construction - Dallas, LLC for the Woodlake Lake Enhancements project, originally approved by council on January 9th, 2024, with a contract amount of $3,587,868.52. The project includes construction of a pavilion, kayak launch platform, concrete step/plant terracing, and a new parking lot. MESA Design Associates, Inc., serves as the design consultant.

 

Two change orders have been executed to date:

 

Change Order No. 1 - Incorporated items not included in the original bid documents. 

Total change order:                                     $230,000.00

Adjusted not to exceed:                      $3,817,868.52

Percent increase:                                                6.50%

 

Change Order No. 2 - Funded a mussel survey required by Texas Parks and Wildlife.

Total change order:                                       $47,110.73

Adjusted not to exceed:                      $3,864,979.25

Total percent increase:                                  7.72%

 

 

Change Order No. 3 provides for additional construction tasks necessary to complete the project, including:

•                     Install storm drain connection from adjacent Woodlake neighborhood and associated improvements.

•                     Concrete pavement replacement along the trail at the intersection of Peters Colony Road and Josey Lane requested by Parks Department; construct a Barrier-Free Ramp (BFR) in the church parking lot

•                     Oncor primary electrical service, including the meter rack, disconnect, conduit installation, and related electrical infrastructure.

•                     Pavement striping revisions along the northeast side of Peters Colony Road.

•                     Preparation of Oncor conduit as-built drawings.

•                     Two additional ADA-compliant ramps at the intersection of Peters Colony Road and Paxton Drive, along with planter topping improvements for the pavilion planters.

•                     Handrail at the kayak retaining wall, together with associated landscaping and irrigation improvements.

•                     Installation of an additional kayak launch accessory equipment to improve safety and accessibility.

•                     Fire hydrant area improvements, including a stone gravity retaining wall, pull box relocation, grading, and backfilling.

 

Total change order:                      $127,078.96

Adjusted not to exceed:                      $3,992,058.21

Total percent increase:                     11.26%

 

This change order will add 0 days to the contract time.

 

Financial Implications:

The contractor’s estimate for the proposed scope is $127,078.96. Funding is available in Account 854360 (Parks Consolidated Fund). This is anticipated to be the final change order for the project.

 

Impact on Community Sustainability:

This project will support the City Council’s strategic objectives and vision of building a community that families and businesses want to call home by:

•                     Improving park and trail safety and accessibility through new ADA ramps, a barrier-free ramp, kayak launch enhancements, and handrail installation, supporting a safe and healthy outdoor environment. (Hospitality; Healthy; Accessible)

•                     Enhancing user experience and wayfinding with updated pavement striping and improved access features that support comfort, clarity, and safety for residents visiting the park and surrounding neighborhood (Hospitality; Engaging; Accessible).

 

Staff Recommendation/Action Desired:

Staff recommends City Council authorize the City Manager to execute Change Order No. 3 with Millis Development & Construction - Dallas, LLC, for additional work on the Woodlake Lake Enhancements Project, in an amount not to exceed $127,078.96, increasing the total construction contract to $3,992,058.21.