Legislation Details

File #: 7823    Version: 1 Name:
Type: Status: Consent Agenda
File created: 11/9/2026 In control: City Council
On agenda: 12/1/2026 Final action:
Title: Consider Authorizing The City Manager To Approve A Construction Contract With American Traffic Construction, LLC Pursuant To ENG BID #2026-08 For The Trinity Mills LED Streetlight Project In An Amount Not To Exceed $281,127.55.
Attachments: 1. Location Map, 2. Bid Tabulation
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

City Council Meeting Date: December 1, 2026

 

Date: November 9, 2026

 

To: Erin Rinehart, City Manager

 

From: Jonathan Wheat, P.E., Director of Engineering

           Shannon Hicks, P.E., Assistant City Manager

 

Title

Consider Authorizing The City Manager To Approve A Construction Contract With American Traffic Construction, LLC Pursuant To ENG BID #2026-08 For The Trinity Mills LED Streetlight Project In An Amount Not To Exceed $281,127.55.

 

Body

Background:

Engineering staff conducts an arterial streetlight analysis and evaluation of candidate corridors through the Arterial Street Light Prioritization process each year and presents this information to the Traffic Advisory Committee (TAC). Based on this process, TAC recommended the installation of streetlighting along Trinity Mills from Marsh Lane to Midway Road. The corridor is an entry point into the City of Carrollton and is adjacent to both commercial and multi-family land uses.

 

This bid is for the installation and construction of arterial streetlights along Trinity Mills from Marsh Lane to Midway Road. Bid notifications were posted online, interested vendors were contacted, and advertisements were placed in the Dallas Morning News. The bid closed on September 22, 2026. Nine vendors submitted a response.

 

The Engineering Department reviewed the submissions. Staff recommends awarding to American Traffic Construction, LLC, who was the lowest responsive and responsible bidder based on price and other factors such as references.

 

Financial Implications:

The Engineer’s Estimate for this project was $320,000. Funding for the project will be purchased with

 

ACCOUNTING UNIT                     ACTIVITY NUMBER                     BUDGET AMOUNT

854460 - Streets Consolidated                     124490499                     $320,000.00

 

Staff recommends the inclusion of a construction contingency to provide an expedient manner to accommodate unforeseen costs and minor additions in work common in all construction projects.  Examples include unexpected conditions discovered during construction, and changes to design that were not possible during plan generation.  All charges against contingency must be supported by detailed pricing information and approved by the City through a formal change order.  However, having advanced Council authorization ensures that work progress is not impeded.  As a cost control measure, the construction contingency for the Trinity Mills LED Streetlight Project is recommended at 5% of the bid amount or $13,387.00.

 

Impact on Community Sustainability:

This project supports the City Council's vision of being "the community that families and businesses want to call home" by improving safety and visibility along a major arterial corridor. The installation of LED streetlighting advances the Council's Hospitality and Economical goals and supports the Vision 2040 Healthy, Accessible, and Engaging aspirations through investment in quality infrastructure, safer transportation corridors, and an enhanced community experience.

 

Staff Recommendation/Action Desired:

Staff recommends that City Council authorize the City Manager to approve a construction contract with American Traffic Construction, LLC pursuant to ENG BID #2026-08 for the Trinity Mills LED Streetlight Project in an amount not to exceed $281,127.55. ($267,740.55 bid & $13,387.00 (5.0%) construction contingency).