Title: Consider Authorizing The City Manager To Approve An Agreement With Road Solutions, LLC Pursuant to Bid #25-008 For Boring and Trenching Services In An Amount Not To Exceed $614,000.00 Annually, For A Total Three-Year Contract Amount Not To Exceed $1,842,000.00.
Attachments: 1. Bid Tabulation 25-008 Boring & Trenching
CC MEETING: JANUARY 21, 2025

DATE: January 9, 2025

TO: Erin Rinehart, City Manager

FROM: Jody Byerly, Director of Public Works
Shannon Hicks, Assistant City Manager

Title
Consider Authorizing The City Manager To Approve An Agreement With Road Solutions, LLC Pursuant to Bid #25-008 For Boring and Trenching Services In An Amount Not To Exceed $614,000.00 Annually, For A Total Three-Year Contract Amount Not To Exceed $1,842,000.00.

Body
BACKGROUND:
This contract will be used by Engineering, Parks and Public Works Departments to prepare multiple sites for the installation of street lighting, traffic signals, and other miscellaneous projects.

On November 4, 2024, the City issued Bid #25-008 for Boring and Trenching. Bid notifications were posted online. Interested vendors were contacted and advertisements were placed in the Dallas Morning News. The bid closed on December 2, 2024. Four vendors submitted a response. Departments reviewed the submissions and selected Road Solutions, LLC based on the lowest responsive bid overall. The award will be for a one-year initial term. The award also includes two additional one-year renewal options, if mutually agreed upon by the City and the vendor, for a potential three-year total contract not to exceed $1,842,000.00.

This vendor has not been used by Carrollton in the past. Based on references from other municipalities, Road Solutions, LLC is in good standing with the City of Coppell and City of Lewisville.

FINANCIAL IMPLICATIONS:
The boring and trenching listed in Bid #25-008 will be purchased from budgeted funds from the cost center and in the amount as listed below.

COST CENTER LINE ITEM BUDGET AMOUNT
404001 - Traffic Operations 63050 and 60920 $100,000.00
854460 - Street Capital Fund 124540499 $506,000.00
353001 - Parks Maintenance 63010 $8,000.00

IMPACT ON COMMUNITY SUSTAINABILITY:
This project supports and aligns with City Council's goals and objectives of properly maintaining...