CC MEETING: August 5, 2025
DATE: July 24, 2025
TO: Erin Rinehart, City Manager
FROM: Jonathan Wheat, P.E., Director of Engineering
Shannon Hicks, P.E., Assistant City Manager
Title
Consider A Resolution Authorizing The City Manager To Negotiate And Execute A Professional Services Contract With BGE, Inc For Engineering Services Related To Intersection Improvements At Old Denton Rd. And Trinity Mills Rd. And Josey Ln. At Trinity Mills Rd. In An Amount Not To Exceed $138,000.00.
Body
BACKGROUND:
This project is to conduct an intersection safety and operations analysis at the two intersections of Josey Lane at Trinity Mills and Old Denton at Trinity Mills. Both intersections have congestion due to high traffic volumes and elevated accident rates. A detailed analysis of both intersections to identify physical and operational improvements will be conducted. The project will evaluate existing signal timing and provide updated signal timing plans for short-term congestion mitigation. Long-term recommendations will also be identified, which may include additional lanes, redistributing existing lanes, signage, illumination, and other access management improvements. Schematic plans and an opinion of probable construction cost (OPCC) will be completed for any recommended interchange alternatives
FINANCIAL IMPLICATIONS:
BGE, Inc has submitted a proposal to the City of Carrollton to perform the engineering services for the project for an amount not to exceed $138,000.00. Funding is available in the Streets Consolidated Fund.
IMPACT ON COMMUNITY SUSTAINABILITY:
This project will support the City Council's strategic objectives and vision of building a community that families and businesses want to call home by:
* Sustaining quality of life - Improvements to the intersection of Old Denton at Trinity Mills and Josey Lane at Trinity Mills will improve the safety and operations of the intersections while minimizing traffic delays.
STAFF RECOMMENDATION/ACTION DE...
Click here for full text