File #: 7459    Version: 1 Name: Change Order 3 The City Hall Basement Remodel Project
Type: Status: Consent Agenda
File created: 11/10/2025 In control: City Council
On agenda: 11/18/2025 Final action:
Title: Consider Authorizing The City Manager To Execute Change Order No. 3 With Gomez Floor Covering, Inc. dba GFC Contracting For The City Hall Basement Remodel Project In An Amount Not To Exceed $28,138.00 Increasing The Total Project Contract To $961,946.00.
Attachments: 1. Location Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
CC MEETING: November 18, 2025

DATE: November 10, 2025

TO: Erin Rinehart, City Manager

FROM: Jonathan Wheat, P.E., Director of Engineering
Shannon Hicks, P.E., Assistant City Manager

Title
Consider Authorizing The City Manager To Execute Change Order No. 3 With Gomez Floor Covering, Inc. dba GFC Contracting For The City Hall Basement Remodel Project In An Amount Not To Exceed $28,138.00 Increasing The Total Project Contract To $961,946.00.

Body
BACKGROUND:
The City Council awarded a contract on February 18, 2025, to Gomez Floor Covering, Inc. dba GFC Contracting in the amount of $855,399.00. The scope of the project is to upgrade interior lighting, replace ceiling tiles and grids, and provide additional open office space in City Hall Basement. Change Orders 1-2 in the amount of $78,409.00 were approved by staff, and included basement floor plan modifications, additional offices on the first floor, new mailroom millwork, HVAC modifications, a domestic waterline relocation, replacement of a drain line under the employee restrooms, and additional electrical and data work.

During the Fire Inspection, the Fire Marshal noted multiple deficiencies in the sprinkler and fire alarm systems that were outside of the contractor's scope of work. The existing sprinkler system needs to be repaired and adjusted to meet the current fire code.

During a door hardware meeting with Facilities and IT, both departments noted that additional door hardware items are needed.

This change order (Change Order 03) in the amount of $28,138.00, will cover the following items:
* Fire Sprinkler system repairs
* Fire Alarm system repairs
* Additional door hardware items

FINANCIAL IMPLICATIONS:
Gomez Floor Covering, Inc. dba GFC Contracting submitted a proposal to the City of Carrollton to cover the above-mentioned items in an amount not to exceed $28,138.00. The revised contract amount (Including Previous Change Orders 01 - 02) would be $961,946.00, a 12.45% increase from the original c...

Click here for full text