City Council Meeting Date: December 1, 2026
Date: November 17, 2026
To: Erin Rinehart, City Manager
From: Jonathan Wheat, P.E., Director of Engineering
Shannon Hicks, P.E., Assistant City Manager
Title
Consider A Resolution Authorizing The City Manager To Negotiate And Execute Contract Amendment No. 1 With Parkhill Architects, L.P. For Additional Professional Services Related To The Oak Creek Tennis Center Project In An Amount Of $47,700.00, Increasing The Total Contract Amount Not To Exceed $690,700.00.
Body
Background:
The City Council awarded a Professional Services Agreement contract on May 06, 2025, to Parkhill Architects, L.P. in the amount of $643,000.00. The scope of professional services includes the design of four new tennis courts and eight new pickleball courts, renovation and expansion of the existing pro shop building, expansion of the parking lot, improvements to the landscape, irrigation, site lighting, and other associated amenities. These improvements are intended to improve the overall functionality, accessibility, safety, and recreational experience of the facility while accommodating increased use and future community needs.
The proposed improvements will modernize and expand the existing recreational facilities to better serve Carrollton residents and visitors. The addition of new courts and expanded support facilities will increase recreational capacity, while improvements to parking, lighting, landscaping, and site infrastructure will enhance operational efficiency and the overall user experience. Collectively, these improvements will support the City’s continued investment in quality recreational amenities and promote the long-term sustainability of the Oak Creek Tennis Center.
This Contract Amendment 01 in the amount of $47,700.00, will include the following professional design items:
• Additional topographical surveying of the Oak Creek Park property
• Preparation of an easement for the underground electrical service t...