File #: 7563    Version: 1 Name:
Type: Status: Passed
File created: 2/23/2026 In control: City Council
On agenda: 3/3/2026 Final action: 3/3/2026
Title: Consider Authorizing The City Manager To Execute Change Order No. 04 With Camino Construction, LP. For Additional Work As Part Of Country Villas Street Reconstruction Project, In An Amount Not To Exceed $18,000.00, Increasing The Total Project Contract To An Amount Not To Exceed $8,065,045.00.
Attachments: 1. Location map
CC MEETING: March 3, 2026

DATE: February 23, 2026

TO: Erin Rinehart, City Manager

FROM: Jonathan Wheat, P.E., Director of Engineering
Shannon Hicks, P.E., Assistant City Manager

Title
Consider Authorizing The City Manager To Execute Change Order No. 04 With Camino Construction, LP. For Additional Work As Part Of Country Villas Street Reconstruction Project, In An Amount Not To Exceed $18,000.00, Increasing The Total Project Contract To An Amount Not To Exceed $8,065,045.00.

Body
BACKGROUND:
The Country Villas Street Reconstruction project includes street, sidewalk, water, and sanitary sewer replacements in the Country Villas Subdivision. City Council awarded the construction contract to Camino Construction, LP on September 10, 2024, in an amount not to exceed $7,556,540.00, with an additional $233,460.00 (3%) approved for construction contingency.
During a sanitary sewer investigation conducted by Public Works, existing sanitary sewer line separations were discovered immediately adjacent to the project limits. Given the proximity to active construction, Staff directed the contractor to perform the necessary repairs, which included relocation of a sanitary sewer manhole, repair of pipe separations, and associated pavement restoration. In addition, field conditions revealed that certain connections to existing sanitary sewer and water mains were not fully accounted for in the original plans and were necessary to complete the project.

Revised quantities have been calculated and verified by both the Contractor and the Design Engineer. This Change Order includes all labor, materials, equipment, and appurtenances necessary to complete the work at the original unit prices. No additional calendar days will be added to the contract time as a result of this Change Order.

FINANCIAL IMPLICATIONS:
The construction contingency was expended via Change Orders No. 01 through No. 03, with Change Order No. 03 requiring Council authorization to cover additional paving...