Legislation Details

File #: 7616    Version: 1 Name:
Type: Resolution Status: Passed
File created: 4/13/2026 In control: City Council
On agenda: 4/21/2026 Final action: 4/21/2026
Title: Consider A Resolution Authorizing The City Manager To Negotiate And Execute Contract Amendment No. 1 With Magee Architects, L.P. For Additional Design Services For The City Hall Remodel Phase II Project, In An Amount Not To Exceed $43,275.00 For A Total Contract Amount Of $293,275.00.
Attachments: 1. Resolution, 2. Location Map
City Council Meeting Date: April 21, 2026

Date: April 13, 2026

To: Erin Rinehart, City Manager

From: Jonathan Wheat, P.E., Director of Engineering
Shannon Hicks, P.E., Assistant City Manager

Title
Consider A Resolution Authorizing The City Manager To Negotiate And Execute Contract Amendment No. 1 With Magee Architects, L.P. For Additional Design Services For The City Hall Remodel Phase II Project, In An Amount Not To Exceed $43,275.00 For A Total Contract Amount Of $293,275.00.

Body
Background:
The City Council awarded a Professional Services Agreement contract on February 06, 2024, to Magee Architects, L.P. in the amount of $250,000.00. The scope of professional services includes design modifications to the lower level to improve the function and security of the IT Department, security enhancements to the first-floor lobby, security enhancements to Council Chambers, security enhancements to the service counters on the first level, and security enhancements to the loading dock.

The first part of the City Hall remodel phase II professional services for the lower level was completed in December 2024. As construction progressed on the lower level, and design services proceeded on the first and second level, and on the exterior, several changes were requested by department heads that would further enhance security while still maintaining exemplary services to our residents and city staff.

This Contract Amendment 01 in the amount of $43,275.00, will include the following professional design items:
* Additional design and construction coordination on the lower level
* Redesign of the reception area on the 1st floor lobby
* Additional design on the exterior to enhance safety for city staff at the breakroom


Financial Implications:
Magee Architects, L.P. has submitted a proposal to the City of Carrollton to cover the above-mentioned items in an amount not to exceed $43,275.00. The revised contract amount would be $293,275.00, a 17.3% increase from th...

Click here for full text