CC MEETING: July 2, 2024
DATE: June 26, 2024
TO: Erin Rinehart, City Manager
FROM: Cory Heiple, Environmental Services Director
Marc Guy, Assistant City Manager
Title
Consider Authorizing The City Manager To Execute Change Order No. 2 With Garrett Demolition, Inc. For The Demolition Of The Structure Located At 1301 South IH-35 East, In An Amount Not To Exceed $22,576.00, Increasing The Total Project Contract To An Amount Not To Exceed $174,865.00.
Body
BACKGROUND:
The structure located at 1301 South IH-35 East, formally known as Van Hyundai, is on a City-owned tract and is being demolished in preparation for future redevelopment in Downtown Carrollton. Van Hyundai has fully ceased operations at this location and has relocated its business.
City Council awarded a contract on April 2, 2024, to Garrett Demolition in the amount of $139,589.00. The scope of the project included the demolition of the structure and foundation, removal of the grit/grease trap, and hydromulching the site post-demolition. Change order no. 1, in the amount of $12,700.00, was approved administratively for the removal and disposal of polychlorinated biphenyl (PCB) fluorescent lighting ballasts and bulbs. During the demolition and excavation of the site a second foundation was discovered under the known foundation. Garrett Demolition provided change order no. 2 in the amount of $6,680.00 for the excavation and disposal of this second foundation.
FINANCIAL IMPLICATIONS:
Garret Demolition submitted a proposal to the City to accomplish the scope of the change order in an amount not exceed $6,680.00. The revised contract amount includes 10% contingency funding for a total amount of $174,865.00, a 14% increase from the original contract amount of $139,589.00. Funding for this work is available from the Transit-Oriented Development Capital Projects Fund.
IMPACT ON COMMUNITY SUSTAINABILITY:
The demolition of this property supports the City Council's strategic Transit Oriented Developmen...
Click here for full text