Legislation Details

File #: 6497    Version: 1 Name: Woodlake Lake Enhancements Project
Type: Status: Passed
File created: 1/4/2024 In control: City Council
On agenda: 1/9/2024 Final action: 1/9/2024
Title: Consider Authorizing The City Manager To Approve A Construction Contract With Millis Development And Construction - Dallas, LLC For The Woodlake Lake Enhancement Project In An Amount Not To Exceed $3,587,868.52.
Attachments: 1. Bidders List, 2. Map, 3. Woodlake Lake Enhancements Phase 1
CC MEETING: January 9, 2024

DATE: January 4, 2024

TO: Erin Rinehart, City Manager

FROM: Jonathan Wheat, P.E., Director of Engineering
Marc Guy, Assistant City Manager

Title
Consider Authorizing The City Manager To Approve A Construction Contract With Millis Development And Construction - Dallas, LLC For The Woodlake Lake Enhancement Project In An Amount Not To Exceed $3,587,868.52.

Body
BACKGROUND:
This contract will provide for the construction of the phase one enhancements at Woodlake Lake. The lake enhancements include a pavilion, kayak launch platform, concrete step/plant terracing and a new parking lot. The construction will demolish the existing pavement and add new sidewalks, trails and landscaping. The project will also improve the electrical and storm drain utilities located at Woodlake Lake.

These renovations and improvements will enhance the recreational value of Woodlake Lake for walking, cycling and kayaking. The pavilion and updated electrical utilities will provide a large space for community events. The additional parking lot will allow for a larger number of residents to access the trails and attend events at Woodlake Lake.

The duration of construction is 270 calendar days. Project signs will be placed at the entrances to Woodlake Lake during construction. Neighborhood residents will be notified in writing regarding the project schedule prior to the start of construction. Additional handouts will be distributed as needed during construction.

FINANCIAL IMPLICATIONS:
Two bids were received on December 19, 2023. The bids ranged from $3,587,868.52 to $5,851,484.00. The low bidder, Millis Development and Construction - Dallas, LLC has done work throughout the Metroplex for various cities on projects of comparable size and scope. City staff contacted references for Millis and they were very favorable.

The 2018 Bond Referendum allocated $2,500,000.00 for the Woodlake Lake Enhancement Project, which is available in the Parks Consolidate...

Click here for full text