CC MEETING: March 3, 2026
DATE: February 23, 2026
TO: Erin Rinehart, City Manager
FROM: Jonathan Wheat, P.E., Director of Engineering
Shannon Hicks, P.E., Assistant City Manager
Title
Consider Authorizing The City Manager To Approve A Construction Contract With Garret Shields Infrastructure, LLC For The Whitlock Addition Street Reconstruction Phase 3 Project In An Amount Not To Exceed $7,007,354.10.
Body
BACKGROUND:
This contract will provide for the reconstruction of four (4) streets in the Whitlock Addition Subdivision including Ryan Avenue, E Russell Avenue, Norris Street, portions of Homer Street, associated alleys, and the parking lot at WJ Thomas Park. The project consists of approximately 6,000 LF of residential street pavement, 4,000 LF of alley pavement, and 2,000 LF of storm pipe. This project was a part of the 2018 Bond Election.
The duration of construction is 540 calendar days. Construction sequencing will ensure that not all streets are under construction simultaneously. Project signage will be installed subdivision entrances, and residents will receive written notice prior to construction. A neighborhood meeting with the residents and the contractor will be held prior to mobilization. Additional handouts will be distributed as required during the project.
FINANCIAL IMPLICATIONS:
Sixteen (16) bids were received on February 11, 2026. The low bid, in the amount of $6,677,354.10, was submitted by Garret Shields Infrastructure, LLC. The Engineer's Estimate for the project was $9,330,000.00. Garret Shields is currently constructing Cemetery Hill Road and Cromwell Drive and has performed satisfactorily so far during construction. They also have positive references from the City of Plano, North Richland Hills, and Highland Village. Funding is available in Account Unit 854460 (Streets Consolidated).
With this neighborhood reconstruction staff recommends the inclusion of a construction contingency. The construction contingency provides an exp...