File #: 2616    Version: 1 Name: Downtown Drainage - Amendment #2
Type: Status: Passed
File created: 4/26/2016 In control: City Council
On agenda: 5/3/2016 Final action: 5/3/2016
Title: Consider Authorizing The City Manager To Approve Professional Services Contract Amendment Number 2 With Walter P. Moore For Modification Of The Completed Drainage Design To Include A Drainage Vault On The IH-35E Frontage Road And Additional Costs Associated With Temporary Paving And Drainage Connections In An Amount Of $56,430.00 For A Revised Contract Amount Of $268,542.00.
Attachments: 1. Location Map
CC MEETING: May 3, 2016

DATE: April 26, 2016

TO: Leonard Martin, City Manager

FROM: Cesar J. Molina, Jr., P.E., Director of Engineering

Title
Consider Authorizing The City Manager To Approve Professional Services Contract Amendment Number 2 With Walter P. Moore For Modification Of The Completed Drainage Design To Include A Drainage Vault On The IH-35E Frontage Road And Additional Costs Associated With Temporary Paving And Drainage Connections In An Amount Of $56,430.00 For A Revised Contract Amount Of $268,542.00.

Body
BACKGROUND:
In July 2014, City Council authorized the design contract for the Downtown box culverts from just east of Broadway on Vandergriff to IH-35E. This was a continuation of the drainage system installed as part of the Union Square project and replacement of an old, undersized box culvert.
Initially Staff assumed that the construction of the Vandergriff section of the box culverts would coincide with the construction of the IH-35E section with which it connects. As the construction phasing of IH-35E became clearer and more defined it became apparent that access to the Downtown area will be restricted with Belt Line Road, the IH-35E frontage road and Vandergriff construction (which impacts Elm and Broadway). By delaying the construction of the drainage structures on Vandergriff, mobility is improved in the downtown area by providing reasonable routes around the IH-35E/Belt Line construction activities.
Unfortunately, delaying of this construction requires significant modification of the current completed design as well as some possible additional costs associated with temporary paving, drainage connections and other modifications. Staff has developed a concept that minimizes temporary structures and paving, but most of the plan sheets will require significant re-work.

FINANCIAL IMPLICATIONS:
Funding for this project was approved as part of the 2013 Bond Program as the Downtown Drainage Improvements.

IMPACT ON CO...