File #: 2834    Version: 1 Name: Old Denton Road (Frankford to Rosemeade)
Type: Status: Passed
File created: 9/12/2016 In control: City Council
On agenda: 9/20/2016 Final action: 9/20/2016
Title: Consider Authorizing The City Manager To Approve A Contract With Tiseo Paving Company For The Old Denton Road Reconstruction Project From Frankford Road To Rosemeade Parkway In An Amount Not To Exceed $7,606,235.60.
Attachments: 1. Location Map, 2. Bidders List
CC MEETING: September 20, 2016

DATE: September 12, 2016

TO: Leonard Martin, City Manager

FROM: Cesar J. Molina, Jr., P.E., Director of Engineering

Title
Consider Authorizing The City Manager To Approve A Contract With Tiseo Paving Company For The Old Denton Road Reconstruction Project From Frankford Road To Rosemeade Parkway In An Amount Not To Exceed $7,606,235.60.

Body
BACKGROUND:
This project was authorized by City Council in 2015 and will provide for the reconstruction of 4,560 linear feet of Old Denton Road from Frankford Road to Rosemeade Parkway along with new sidewalks, LED street lighting, landscaping, irrigation and the rehabilitation and updating of the Dudley Branch bridge with new railing and stone fascia.
Because the project will affect traffic on Old Denton Road for several months, the project was bid using the A+B bidding model whereby the contractor determines his cost (A) to construct the project and the number of days to complete the work. The value of a day, which for this project was set at $2,000, times the number of days is cost (B). The total of these two amounts determines the contractor's total bid amount, although the contract amount to the City is cost A. If the contractor completes the work earlier than the number of days bid, he will receive an incentive amount of the number of days the project is completed early times $2,000. If he is late, he will pay a disincentive amount of the number of days late times $2,000. The maximum incentive he can receive is $120,000.
Construction will be phased so that two lanes of traffic are open at most times. There will be times during non-rush hour periods where traffic will be reduced to one lane around the bridge since traffic can't be moved to the median area. Project signs will be placed at the ends of the project area during construction. The project has been placed on the monthly Construction Update and is included in the City's web site. Most trees located within the median will be r...

Click here for full text