File #: 5151    Version: 1 Name:
Type: Status: Passed
File created: 2/18/2021 In control: City Council
On agenda: 3/2/2021 Final action: 3/2/2021
Title: Consider Authorizing The City Manager To Approve A Contract With 3D Paving And Contracting, LLC For The A.W. Perry NOTICE Street Reconstruction Project In An Amount Not To Exceed $1,836,847.45.
Attachments: 1. Location Map, 2. AW Perry Maps, 3. A.W. Perry Street Reconstruction Bid Tabulation
CC MEETING: March 2, 2021

DATE: February 17, 2021

TO: Erin Rinehart, City Manager

FROM: Jonathan Wheat, P.E., Director of Engineering
Marc Guy, Assistant City Manager

Title
Consider Authorizing The City Manager To Approve A Contract With 3D Paving And Contracting, LLC For The A.W. Perry NOTICE Street Reconstruction Project In An Amount Not To Exceed $1,836,847.45.

Body
BACKGROUND:
The A.W. Perry neighborhood was originally developed in the 1930s and 1940s. This is a NOTICE project and will elevate the neighborhood infrastructure to coordinate with many of the Downtown Carrollton/TOD area features, including curb and gutter streets, streetlights, sidewalks, and brick paver entry ribbons from Denton Drive. This contract will provide for the reconstruction of five streets in the neighborhood, including Cotton Street, Pear Street, Palm Street, North Main Street, and Jackson Street. The project consists of the installation of approximately 2,405 linear feet of residential street pavement, 2,300 linear feet of sidewalks, 2,130 linear feet of 8" water line, 1,170 linear feet of 8" sanitary sewer line, 480 linear feet of storm sewer pipe, and 11 streetlights.

The duration of construction is 320 calendar days. Construction will be performed such that all streets will not be under construction at one time. Project signs will be placed at the entrances to the subdivision while it is under construction. The project has been placed on the monthly Construction Update and is included on the City's website. All residents will be notified in writing regarding the construction schedule prior to the start of construction. Also, a neighborhood meeting with the homeowners and the contractor will be held prior to construction. Additional handouts will be distributed as required during the project.

FINANCIAL IMPLICATIONS:
Thirteen (13) bids were received on January 28, 2021. The low bid, in the amount of $1,836,847.45, was submitted by 3D Paving and Contracting, LLC. The engi...