File #: 6209    Version: 1 Name: Contract - Northland Estates Paving & Utility Improvements - Contract KIK Underground, LLC
Type: Status: Passed
File created: 6/12/2023 In control: City Council
On agenda: 6/20/2023 Final action: 6/20/2023
Title: Consider Authorizing The City Manager To Approve A Construction Contract With KIK Underground, LLC For The Northland Estates Paving and Utility Improvements Project In An Amount Not To Exceed $5,266,909.50.
Attachments: 1. Bidders List, 2. Location Map
CC MEETING: June 20, 2023

DATE: June 12, 2023

TO: Erin Rinehart, City Manager

FROM: Jonathan Wheat, P.E., Director of Engineering
Marc Guy, Assistant City Manager

Title
Consider Authorizing The City Manager To Approve A Construction Contract With KIK Underground, LLC For The Northland Estates Paving and Utility Improvements Project In An Amount Not To Exceed $5,266,909.50.

Body
BACKGROUND:
This contract will provide for the reconstruction of five streets in the Northland Estates Subdivision, including Northland Street, Evergreen Street, Greenmeadow Drive, Greenhill Drive, McCoy Court and associated alleys. The project scope consists of the reconstruction of approximately 7,400 linear feet of residential street pavement, 3,900 linear feet of alley pavement, 4,200 linear feet of water lines, 4,300 linear feet of sanitary sewer lines, 700 linear feet of storm drainage pipe and 110 linear feet of drainage channel. This project was approved by the voters as part of the 2018 Bond Election.

The duration of construction is 300 calendar days. Construction will be performed such that all of the streets and alleys will not be under construction at the same time. Project signs will be placed at the neighborhood entrances during construction. Residents will be notified in writing regarding the construction schedule prior to the start of construction. A neighborhood meeting with the residents and the contractor will be held prior to construction. Additional handouts will be distributed as needed during the project.

FINANCIAL IMPLICATIONS:
Four bids were received on June 8, 2023. The low bid, in the amount of $5,266,909.50, was submitted by KIK Underground, LLC. The engineer's estimate for the project was $5,638,280.00. KIK Underground has satisfactorily completed similar projects within the past three years. Funding is available in the Streets Consolidated Account, Drainage Consolidated Account and the Utility Consolidated Account.

IMPACT ON COMMUNITY SUSTAINABIL...