File #: 6388    Version: 1 Name: Change Order #2 Crosby Estates Section 1 Paving & Drainage Improvements
Type: Status: Passed
File created: 10/19/2023 In control: City Council
On agenda: 11/7/2023 Final action: 11/7/2023
Title: Consider Authorizing The City Manager To Execute Change Order No. 2 With 3D Paving And Contracting, LLC For Additional Work As Part Of The Crosby Estates, Section 1 Paving and Drainage Improvements Project, In An Amount Not To Exceed $60,400.00, Increasing The Total Project Contract To An Amount Not To Exceed $3,929,865.37.
Attachments: 1. Location Map
CC MEETING: November 7, 2023

DATE: October 19, 2023

TO: Erin Rinehart, City Manager

FROM: Jonathan Wheat, P.E., Director of Engineering
Marc Guy, Assistant City Manager

Title
Consider Authorizing The City Manager To Execute Change Order No. 2 With 3D Paving And Contracting, LLC For Additional Work As Part Of The Crosby Estates, Section 1 Paving and Drainage Improvements Project, In An Amount Not To Exceed $60,400.00, Increasing The Total Project Contract To An Amount Not To Exceed $3,929,865.37.

Body
BACKGROUND:
City Council awarded a contract on June 6, 2023, to 3D Paving and Contracting in the amount of $3,831,573.37. The scope of the project is to replace street, sidewalk and alley pavement throughout the Crosby Estates neighborhood, including Milam Way, Milam Circle, Sam Houston Boulevard, Sam Houston Circle, Reagan Boulevard and five alleys. Change order no. 1, in the amount of $37,892.00, was approved administratively on July 19, 2023, and was for additional storm sewer work along Milam Way which was required to bring the system up to current City standards.

Change order no. 2 is in the amount of $60,400.00, and will cover the following items:
* Maintenance of temporary security fencing installed along Webb Chapel Road. Until a new contractor can be hired to complete the screening wall project, 3D Paving and Contracting will provide maintenance of the existing temporary fence.
* Install a 7' x 8' storm sewer junction box.
* Remove and re-construct a railroad tie wall adjacent to a sidewalk.
* Remove and replace rail for an existing sliding security gate on a driveway approach.
* Remove and reset mailboxes.
* Install 10" sidewalk curb in lieu of a retaining wall.
* Replace/adjust existing water services.

FINANCIAL IMPLICATIONS:
3D Paving and Contracting submitted a proposal to the City to cover the above-mentioned items in an amount not to exceed $60,400.00. The revised contract amount will be $3,929,865.37, a 2.57% increase from the original ...