CC MEETING: April 2, 2024
DATE: March 25, 2024
TO: Erin Rinehart, City Manager
FROM: Jonathan Wheat, P.E., Director of Engineering
Marc Guy, Assistant City Manager
Title
Consider Authorizing The City Manager To Execute Change Order No. 2 With KIK Underground, LLC For Additional Work As Part Of The Northland Estates Paving And Utility Improvements Project In An Amount Not To Exceed $50,849.00, Increasing The Total Project Contract To An Amount Not To Exceed $5,320,873.04.
Body
BACKGROUND:
City Council awarded a contract on June 20, 2023, to KIK Underground, LLC in the amount of $5,266,909.50. The scope of the project is to replace streets and sidewalks throughout the Northland Estates neighborhood. Change order no. 1, in the amount of $3,114.54, was approved administratively on July 28, 2023. It was for increasing the size of a sanitary sewer pipe as required by the City's Wastewater Collection System Master Plan.
Change order no. 2 is in the amount of $50,849.00, and will cover the following items:
* Additional water line and utility work to install an additional fire hydrant;
* Increase the thickness of the bottom slab of the concrete channel;
* Additional tree removal requests by property owners and within the rights-of-way.
The duration of construction will not be affected and remains at 300 calendar days.
FINANCIAL IMPLICATIONS:
KIK Underground, LLC submitted a proposal to the City to cover the change order in an amount not to exceed $50,849.00. The revised contract amount will be $5,320,873.04, which is an increase of 1% from the original contract amount. Funding is available in the Streets Consolidated, Drainage Consolidated and Utility Consolidated funds.
IMPACT ON COMMUNITY SUSTAINABILITY:
This project will support the City Council's strategic objectives and vision of building a community that families and businesses want to call home by:
* Sustaining quality of life - Improvements in the subdivision should improve the appearance...
Click here for full text